Friday 25 November 2016

Electrical rough in appointment.

Today was our electrical rough in appointment, and we got a new site supervisor so we met him also.

The appointment went well, we only had a couple of issues-

  • Wall bracing missing in Study/Garage wall.
  • Missing Cat6 data point in kitchen.
  • Light and Oven isolation switch needs lowering.
  • Outdoor power point at 600mm high instead of 2600mm high.
  • Gas point missing in the alfresco area.


The new site supervisor seems real good and believes we should be in for the start of February :)

The next step is the plumbing installation (already meant to be done but hasn't been) then the wall insulation gets installed. these are booked in for the 29th and 30th of November.

Tuesday 22 November 2016

We are at lock-up...

The front and back doors have been installed and the Soffit has been installed, garage doors are coming early December. The wooden posts at the front of the house has also been installed. Electrical rough in has started and should be complete this week.


Western side of the house.


Front of the house.


Back and western side of the house.

Monday 7 November 2016

Roof and Guttering Complete

The root and guttering has been completed. now they start the insides :)


Western side of the house.


Front of the house.