Saturday 24 December 2016

Garage door installation

The front garage door has been installed and it goes with the rest of the house great.


The site supervisor called to say that the waterproofing and everything has been completed and the fit-out will begin on the 10th of January 2017. Hopefully we will be in by the end of February 2017.

Thursday 15 December 2016

Site visit today

We had a site visit today and everything is good except for a couple of things.

They plastered over one of the shower recesses and the kitchen switches haven't been lowered.

Everything else looks great, the cornice and garage doors will go up next week and the first stage of waterproofing should happen before Christmas also.

The fix-out is scheduled for just after Christmas and the SS believes we are still good for the February contact date.

Wednesday 14 December 2016

Plasterboard installation.

We visited the site on the weekend and the plasterboard installation was complete, the walls are up and the joins were sealed. However the cornice still needs to go up.

We have a meeting onsite tomorrow to go for a walk through and check everything out, hopefully the issues found in the electrical walk through have been fixed. Will find out the next steps and when things are booked in.

It is starting to look more like a house on the inside and we are getting excited, handover in February could actually happen.